Dear Stakeholder
I’m writing with an update about our ongoing work to upgrade the gas network in Deal. This information is also available on our website here https://www.sgn.co.uk/our-gas-works/major-planned-projects/deal-a258-london-road
Our upgrade work is progressing well, and we’ve now installed around 1.2km of new, long-lasting plastic pipe along London Road, The Street and Darracot Close.
We are on schedule to begin phase two, with a road closure on London Road between the junctions of Manor Road and Haywards Close from Wednesday, 23 July for approximately six weeks.
We’re sorry for the disruption this phase of the work may cause, but it really is vital to keep the gas flowing safely. We’ll be working extended hours to complete this work as quickly and as safely as possible.
Kind Regards
Helen Peile, Stakeholder and Community Manager
SGN, St Lawrence House, Station Approach, Horley RH6 9HJ